Short answer: Construction invoices can be factored, but fewer factors will do it, and the ones that do work differently. Pay applications, retainage, lien waivers, backcharges and pay-when-paid clauses make a construction receivable less certain than a normal invoice, so construction factors look hard at the general contractor’s credit and paperwork, advance only on approved billings, and usually don’t advance on retainage at all.
An electrical contractor moving into larger commercial and government work described his receivables on one of our calls: “I would say normal is net 30. But again, a lot of times it’ll be, especially on bigger ones, it says net 30, it leaks to 45 or 60.” Asked about retainage, he said, “Sometimes they’re an average of 5% or 10% of the project, so they can be significant, especially when they slow pay those.” Payroll goes out weekly and materials are due in 30 days, so subcontractors in that spot start asking about factoring.
Why many factors avoid construction
A standard factor buys an invoice for finished work that the customer owes in full (the basics are in invoice factoring). A construction receivable is messier:
- Progress billing. A pay application bills for a percentage of work complete. The GC, architect or owner can revise that percentage before approving it, so the “invoice” can shrink after you submit it.
- Retainage. Usually 5% or 10% of each billing is held until the job, or your scope, is finished and accepted. That money may sit for months or longer.
- Lien waivers. GCs want waivers before or with each payment. A factor has to make sure the waivers you sign don’t give away rights tied to money it advanced.
- Backcharges and setoff. The GC can deduct for cleanup, delays, damaged work or problems on another job and pay you less than the approved amount.
- Pay-when-paid and pay-if-paid clauses. Your payment can depend on the owner paying the GC first. Depending on the wording and your state’s law, that can delay payment or, in some states, shift the risk of owner nonpayment onto you.
- Disputes and change orders. Unapproved change orders, punch lists and scope disagreements can hold up a pay app.
What construction-specific factors look for
The factors that work in construction underwrite the general contractor (and sometimes the project owner) as much as your company, because the GC is the one paying. Expect them to ask for:
- The GC’s payment history and credit, and sometimes whether the project is bonded
- Your subcontract, so they can read the payment terms, retainage, pay-when-paid language and any clause limiting assignment
- An approved or signed pay application, not just one you submitted
- Conditional lien waivers and proof that your suppliers and lower-tier subs are being paid
- Joint check agreements on larger material orders, where the GC writes checks to both you and the supplier
- A clean UCC and debt picture
A commercial contractor we talked with had taken on several merchant cash advances with weekly payments while waiting to get paid on three large projects. Paul Childers told him, “any project funder who does project-based funding or any company that would consider factoring, they won’t even look at you until these MCAs are gone anyway.” Most factors want a first-position claim on receivables, and those advances usually already hold one. See daily payment loans and merchant cash advances for why.
What it costs
Factoring fees are quoted per period, often per 30 days, and the total depends on how long the GC takes to pay. A construction law article from the American Bar Association describes rates generally running from 2% to 15% and moving with payment timing. On a call with a commercial contractor, Paul Childers put typical factoring costs at roughly 1.25% to 3.15% every 30 to 60 days. The slower the GC, the more periods you pay for.
Here is a simple example. You bill a $100,000 pay app, and 10% retainage leaves $90,000 currently due. A factor advances 80% of that, or $72,000, and charges 3% per 30 days on the $90,000. If the GC pays in 30 days, the fee is $2,700. If it pays in 60 days, the fee is $5,400. If it slips to 90 days, the fee is $8,100. Add any setup, wire, lien search or monthly minimum fees, and run the total against your job margin before you sign.
Also check whether the agreement is recourse (you buy back invoices the GC doesn’t pay within a set time) and whether you have to factor every invoice from that GC or can pick and choose.
Notice of assignment and what GCs think of it
Construction factoring is almost always done with notice. The factor sends the GC a notice of assignment telling it to pay the factor directly. Under the Uniform Commercial Code as adopted in most states, once a GC receives proper notice, paying you instead may not count as payment, and the GC could have to pay twice.
Some GCs handle factoring routinely and just update the payee. Others see it as a sign the sub is short on cash and worry about who will pay the sub’s suppliers and crews. If a supplier goes unpaid and files a lien, the GC has to deal with it even though it already paid the factor. Some subcontracts try to prohibit assignment of receivables, and whether that clause holds up depends on state law. Talk to the GC’s project manager before the letter arrives.
Government work adds another layer. Federal contracts have their own assignment rules, and state and local agencies have theirs, so confirm with the factor and your attorney how payments on a public job can be assigned.
How retainage is handled
Most construction factors don’t advance on retainage, because it isn’t due until closeout, which punch lists, paperwork or another trade’s problems can delay. On federal jobs, retainage is capped at 10% of the approved amount and must be released promptly once the contract is complete. Many states have their own caps and release deadlines for public and sometimes private work.
On a $1,000,000 subcontract with 10% retainage, that is $100,000 of earned profit and overhead you are carrying until the end of the job, whether or not you factor the rest. Some factors will buy retainage once it is due and the paperwork is complete.
Mechanics lien rights and factoring
Mechanics lien rights belong to the parties who furnished labor or materials to the property, and each state sets the rules for notices, deadlines and who can enforce them. When you sell a receivable, whether the factor can step into your lien rights, or rely on them at all, varies by state.
Two practical issues come up often. First, the lien waivers you sign to get paid can waive rights on amounts the factor funded, so the factor will want a say in which waivers you sign and when. Second, if you use factoring money on payroll and don’t pay a supplier, that supplier can lien the job, and the GC can deduct what it pays to clear the lien from what it owes you, which then becomes your problem with the factor. Have a construction attorney review the factoring agreement and your lien procedures together.
Alternatives to look at
- A bank line of credit secured by receivables. A bank AR line usually costs less than factoring and doesn’t require notice to the GC. Banks typically lend against a borrowing base that leaves out retainage and receivables past 90 days. See accounts receivable financing.
- Supplier terms. Longer terms from your main supply house, job accounts and joint check arrangements push material costs closer to when you get paid.
- Contract terms. Billing cutoffs, retainage reduction at 50% complete, mobilization billing and shorter pay cycles can sometimes be negotiated before you sign. A commercial painting contractor that had carried $750,000 or more in receivables at 65 to 75 days told us they were shifting toward direct-to-owner work and “away from general contractors that have much longer pay terms.”
- Mobilization or project funding. Some funders advance money at the start of a job against the contract. Some are structured like merchant cash advances, with daily or weekly payments that start before your first pay app is approved, and they can block factoring or a bank line later.
The gap tends to widen as jobs get bigger. A commercial contractor with three large projects starting at once said of his lower-tier subs, “the problem is these subs are a lot smaller, so they can’t afford to not get paid,” which meant he carried their costs until the GC paid him. Our articles on why profitable trades businesses run short on cash and financial risks as you grow cover how to plan for that before the next large contract.
This article is educational and isn’t legal, tax, accounting or lending advice. Program rules, lender terms and credit bureau practices change, so verify current terms before acting.